FAQs - Updated November 2025
- The park consistently feels unsafe and unwelcoming. Illicit activities occurring during the day and often throughout the night discourage legitimate park use by Whiteaker neighbors and visitors. This has been a decades-long problem, and while there have been numerous attempts at reclaiming the park, these difficult issues persist today. These illicit activities adversely affect the daily lives and property of neighbors immediately abutting the park site. Children and families who desire to use the park are particularly negatively impacted as the playground structure is continuously mis-used as a shelter for drug use and overnight camping. They also negatively affect the safety of Parks staff working to maintain the park as a safe and welcoming space. And despite regular and additional daily maintenance, regular security visits, and continuous expenditure on routine repairs, the park remains underused and unsafe for many.
- The lack of paved walks makes most of the park inaccessible to visitors with impaired physical mobility. The park has limited paving at the entrances and a sidewalk along the street frontage but otherwise has no paved or accessible routes upon which to walk or wheel. As such, only fully able-bodied visitors can fully experience the park as the existing paths are not ADA compliant.
- The park amenities that remain are in significant disrepair. In the name of preventing illicit activities, all park furniture and low-level vegetation have been progressively removed over time by Parks staff. The playground is out of date, aging and chronically misused as shelter by people experiencing homelessness. Park signage, lighting, fencing and other amenities are also well past their useful life and need renovation or replacement.
- Information gathering – Gather existing conditions, identify problems, needed improvements, and park use patterns.
- Development of two or more design proposals and feedback – Develop design proposals to address information gathered in Step 1 and gather stakeholder feedback on these proposals.
- Consolidation of information from Step 2 into one “final” design proposal– Make design adjustments per design feedback and share the completed design with the public.
- Help Scobert Gardens feel safer, more welcoming and comfortable for all visitors.
- Renovate the playground and keep it closer to the front of the park.
- Make the playground bigger with more activities and assure shade over it.
- Keep the trees and increase shade.
- Make the park more accessible for all users and a windy path design is preferred.
- Include a stage and small plaza area for more event programming in the park.
- Add site furniture throughout the park.
- Open up more of the park to public use.
- Re-use the basalt columns currently at the park entry.
- Add a public restroom now shown in the West 4th Ave. right-of-way.
- Reduce the amount of concrete from earlier design proposals in paths and stage areas – smaller stage and paths reduced to 5’ width.
- Add more trees to the main lawn
- Adjust playground a little further south from the street for safety
- Renovate “dogleg” area to provide community garden spaces for use by non-profit partners.
- Keep the existing fencing where it is currently located along the south side of the park. See FAQ #8 for more information on this.
- Open the “dogleg area” to a fully publicly accessible community garden. See FAQ #9 for more information on this.
- Inclusion of a native plant garden and interpretive signs in the existing play area space. Survey responses support moving the playground to the front of the park, so this area will be re-used for the renovation of the playground. In addition, park operations staff do not have the capacity to maintain specialty gardens in neighborhood parks so planning staff are reluctant to include this type of feature knowing that it won’t be successful over time.
1. What has been the public process to date for the Scobert Gardens Park Renovation project?
City of Eugene Parks and Open Space staff began a public process for renovation of Scobert Gardens Park in the fall of 2017. Staff capacity issues and the Covid pandemic delayed project progress until early 2023 when planning efforts restarted with the assistance of landscape architecture consultants from the Eugene office of Cameron McCarthy Landscape Architecture and Planning.
The City hosted an initial project meeting with the community in May of 2023 followed by a park tour and discussion in June of 2023. In an initial survey, 98 people shared their hopes for, as well as concerns about, the renovation of the park. Using this information, planners developed two different park designs for the community’s consideration.
The City hosted a second public meeting in September of 2023 to share the designs and garner community feedback and discussion. An additional option, developed independently by neighbors, was also shared at the second public meeting. In the second survey, 58 people responded to the two designs. These responses, along with some ideas in the neighbor-generated plan, were incorporated into the third design and survey in June of 2024.
The third design was available for public comment through mid-August of 2024. The City received over 120 responses to the online survey, around 40 responses to an on-site survey associated with a self-guided tour, and several emails from neighbors sharing their thoughts and opinions on the design. Cameron McCarthy’s work concluded at the end of this phase of design, and the City is now proceeding with the completion of the design process.
Parks Planning staff have completed a 4th design proposal which is now available along with the results of both the on-line and on-site self-tour surveys from July of 2024.
2. What are the current issues facing Scobert Gardens Park?
3. Is this fourth plan the final design and will the park be built exactly as shown?
This fourth design responds to the significant feedback the City received on the third design, and the City remains committed to development of a design that feels welcoming and safe for all visitors. While it is likely that some changes will be made as staff develop construction documentation and the project goes through the Historic Review Board permitting, this plan is representative of what the City is planning to construct.
4. What has been the design and planning process to date for the renovation of Scobert Gardens Park?
Parks and Open Space staff typically plan for a three-step process to garner stakeholder feedback and propose designs that respond to what we’re hearing. Stakeholders include park neighbors and advocates, park users, park partners, park operations staff and park ambassadors.
The three steps are as follows:
For the Scobert Gardens Park project, additional design work was required to consider feedback about the third design which has now been incorporated into a fourth concept design plan for the park.
5. What public feedback has been incorporated into the current design?
6. What feedback has not been incorporated into the design?
7.Why would the City propose fencing a public park?
Installation of a fence along the West 4th Avenue frontage of Scobert Gardens Park is now included in the plan as a publicly supported park feature. While we understand that retaining the front fence in the design is not supported by some, nearly 60% of the survey responses received from the neighborhood were supportive of this approach. In addition, we received significant feedback that it wasn’t worth building new park features without it as night-time vandalism would render the park improvements regularly damaged or un-maintainable. This feedback is substantiated by past experience.
While Eugene’s parks have traditionally not been fenced, the ability for Parks to close gates at Scobert Gardens overnight will reduce the instances of overnight illicit activities, consistent vandalism to park property, behavioral impacts to adjacent properties, and misuse of park amenities. The City cannot provide the personnel required to enforce park rules overnight throughout the year and it is more cost effective to construct a fence with one-time dollars than to provide consistent ongoing operational dollars. By reducing the significant operational time and dollars spent on security and vandalism, more resources can be directed to the maintenance and upkeep of the park.
All parks in Eugene close at 11:00 p.m. nightly, so this will not be a change in park rules or policy. Park fencing allows for the park to be cleared prior to gate closure each evening. It also allows for a much easier reset of the park each morning by operations staff due to a reduction in the amount of litter and vandalism to be addressed. There are gates that are closed every night at parking lots throughout Eugene’s Park system so this is not a new concept or operational challenge. We have worked with contractors for years to ensure gates are opened each morning and closed each night.
Staff are committed to a fence design that will be attractive, will function as a welcoming gateway when open, and will allow for future decoration, rotating art or whatever is appropriate for the spirit of the Whiteaker to be reflected on the fence. To the greatest degree possible we want the park to feel open and welcoming during park hours, band the park amenities to be protected overnight.
8. Why is there a fence at the back of the park and will it be there after the renovation?
The fence at the south end of the park currently limits access to about 1/2 of the entire park property and was installed in 1998 to create a buffer between the park and the neighboring properties to the south. Neighbors on West 5th Avenue, whose backyards abut park property, were consistently experiencing vandalism, theft, extreme noise and more from illicit activities originating in the park. The installation of the fence along the alignment of the original park path closed off access to a large area of the park but also significantly improved day-to-day conditions for adjacent neighbors.
Parks staff have been working with these neighbors to evaluate the need for and location of the fence. This fence remains a vital buffer for the neighbors and will be retained. A new fence location is now shown 20’ north of the existing south neighbor fences to maintain this buffer while increasing the usable area of the park.
9. Why is a section of the park not accessible to the public and what’s the plan for this area when the renovation is complete?
The “dogleg area,” as it’s called, refers to the southwest corner of the park which has low visibility and has been fenced off from public use due to illicit activities for many years. This space was originally envisioned as an open park space then managed as a community garden by a Eugene-based non-profit organization. When the community garden partnership ended, the area became a haven for negative behaviors, significantly impacting adjacent park neighbors, and was fenced off.
In 2021, the City entered into a park adoption agreement with neighboring property owners to allow them to assist in the maintenance and operation of the dogleg area. The partnership has resulted in the activation of the space as neighbors have invested in keeping the vegetation in check and constructing raised beds for vegetable gardening.
We have heard from the community that they desire a more public-facing partnership for this area. The City is committed to this goal while preserving the partnership with neighbors and plans to add a non-profit as a third partner to the park adoption agreement. The non-profit partner will be one that programmatically benefits underrepresented communities in Eugene and may change from year to year depending on their ability to program the site. Lastly, the park renovation project will include construction of new and highly durable raised beds, more accessible pathways, and associated water supply to support the ongoing activation of this historically important activity in Scobert Gardens Park.
10. Will there be a new restroom in Scobert Gardens Park?
A restroom is currently proposed immediately outside of the park in the West 4th Avenue right-of-way. The construction of the restroom will somewhat depend upon the ability of Parks staff to maintain the restroom as clean and safe for public use in the future. This location must also be approved by the Historic Review Board permitting process prior to construction. Budget limitations may result in a site that is plumbed and ready for future installation but also serves as a location for seasonal restroom placement.
11. How can we get more shade into the park?
City staff understand the importance of shade and cooling that public parks can provide on extremely hot days. Parks increasingly have a role in mitigating the negative effects of climate change and we take this responsibility seriously.
Additional tree plantings are shown in this latest design and placed with an eye toward maintaining some sunny areas in the park. In addition, as an agency, we are beginning to incorporate shade structures into our new and renovated playgrounds and will likely do so at Scobert Gardens Park.
12. Could more trees and shrubs be added to the design?
Yes, more trees have been added to the design. Shrub beds have been historically difficult to manage and maintain due to regular camping and illicit use, but this doesn’t rule out select application of shrub or perennial planting as part of the park improvements. Some small shrub beds have been added to the design along the frontage of the park together with new trees in the lawn area.
13. Will the park include any public art or decoration celebrating the Whit?
Yes! Staff are excited to explore opportunities for this type of collaboration, and we’ll dive into those details now that we’ve landed on a site design. We think the entry fence especially holds potential, but we will also continue to look at other art or interpretive opportunities for the park.
14. Where can I find more information?
On this project page, you can find the results of the first two surveys, previous design ideas, and take the survey for the most recent design proposal.
15. Who can I talk to or connect with to talk about this project?
Project Manager: Emily Proudfoot, Principal Landscape Architect
Asst. Project Manager: Rex Redmon, Landscape Designer